Company NameStreetCity, State Postal Code |
Tuesday, June 6, 2023
First Name Last Name |
e: Email |
Company Name |
t: N/A |
Street |
f: N/A |
City, State Postal Code |
|
Project:
|
Project |
Ref:
|
Reference |
Dear First Name:
According to the contract documents on this project, no interference with our work was
shown or detailed in any way. As you know, we have encountered substantial interference
in the areas of Areas of Interference
and this will confirm that we have been direct to incur additional costs as a result of
this interference and that we will look to you for reimbursement of all costs and
expenses so incurred. Furthermore, any delays resulting from this additional work will
entitle us to a commensurate extension of contract time.
If you have any questions, please do not hesitate to contact me.
Company Name
First Name Last Name
Title
Email
Telephone